PAINT SCHEDULE

Eagles Reserve Paint Schedule 

Phase III (Arabian Lane Townhouse)
The below schedule is PROJECTED and will be subject to change due to weather, holidays, etc. 
Please make sure NO DECORATIONS are put up for units/building scheduled around the holidays as they will
interfere with the paint project.
P&R will be held harmless for any damage done to decorations

Phase II (Lago Vista) Started May 19, 2016 - Completed 9/21/16

Phase II (Lago Vista)

 Started May 19, 2016 - Completed 9/21/16   


The colors selected are final. K&K Architect designed building paint color & schemes which were reviewed and approved by the Eagles Reserve HOA Board. NOT subject to change.


The schedule above shows the Phase I: Arabian Lane Villa's paint sequence, Phase II: Lago Vista, Phase III: Arabian Lane Town Homes. The project, work scope, and timing is established by the painting contractor P&R. This schedule will be updated often.

Tuesday, March 22, 2016

Why are some buildings being skipped?

Those are the buildings with one or more units in need of repair.

What happens if the repairs are not completed when it is time to paint my building?

If one of the units has not completed repairs by the time it is scheduled to be painted, the entire building will be skipped. Check the schedule to see the status of each building and whether the building is ready to be painted.