Friday, November 4, 2016

UPDATE:


Apologize for not updating everyone in a timely manner. 


The good news is that Phase I - VILLAS and Phase II - LAGO VISTA has been completed. 


Here is an update on where the project stands so far:
Please find posted under "SCHEDULE" a projected schedule of Phase III. P&R is working (3) crews and if all goes well, the paint project should be completed before thanksgiving. 

Screen Repair- Nathan's Rescreening and Repairs has taken over the Rescreening job. Please visit the post about screening for full information. 

Holiday Decorations:  If your building is scheduled to be painted over the holiday season, please do NOT put up any decorations as it will hinder the paint project. Damage to your decorations are solely the liability of the homeowner and P&R will be held harmless.

ARABIAN LANE TOWN HOMES:
Please make sure you have all your patio furniture either put outside or placed in the middle of your patio and cover it with a tap. P&R will not be held responsible for any damage due to owner not securing or properly covering their belongings. 

Building #4 will be skipped for a short period of time so an owner can complete renovations. 

Keep updated with relevant information on the blog: 

ERPaint.Blogspot.com 

Thank you for your patience. It will all be over soon!






Tuesday, October 11, 2016

HOLIDAY DECORATIONS

Decorations: Please, if your building has yet to be painted, we ask that owners/renters DO NOT put up any decorations: Halloween, Thanksgiving or Christmas. 

P&R will NOT be held responsible for any damage to these decorations should an owner/renter put them up anyway. 


Wednesday, August 24, 2016

Weatherstripping

P&R will no longer install new weatherstripping effective 8/24/16

If P&R paints the front door while it is shut, and they do not remove the weatherstripping, there is a chance of the door sticking. The easiest way is to take the weather stripping out and give the owner some tape to tape up the inside of the door for the night while the door it being painted.

If they cannot get entry, then P&R will just paint the door while it is closed.


Friday, June 3, 2016

Why is a building being skipped?

A building is skipped or not pressure-washed or painted because one or more of the units has not been repaired and/or those repairs not approved by P&R

Tuesday, May 31, 2016

In What Order Will The Buildings Be Painted?

Phase I was the villas.
Phase II is Lago Vista which is in progress now.
Phase III will be Arabian Lane Town homes. Start date on this phase will be posted here.


Friday, May 6, 2016

Will P&R Replace the Weather Stripping in the Door?

Yes, P&R will replace the weather stripping in the front door at your request. The cost is $25.00. Please get with Craig, site manager, and inform him that you want it done.



Tuesday, March 29, 2016

Are the units being pressure (power) washed prior to being painted?

Every building gets pressure washed and cleaned with chlorine. It is then inspected by a P&R representative and a Sherwin Williams representative before painting.