Tuesday, May 31, 2016

Can my colors and or color scheme be changed.

No. The colors are part of the master architectural design put together by the architects (Klar and Klar).

In What Order Will The Buildings Be Painted?

Phase I was the villas.
Phase II is Lago Vista which is in progress now.
Phase III will be Arabian Lane Town homes. Start date on this phase will be posted here.


Monday, May 30, 2016

Why do I have to park my car in the parking lot when you are painting my building?

Between  the  hours  of 8:00 am and 6:30 p.m., we will be spraying the building and using the driveway. We don't want anyone to get over-spray on there vehicles. 

The garage door should not be opened or closed while we are working as we use a sprayer to dispense the paint. This is why we recommend you park your car in the parking lot during the above hours. 

A villa should take a minimum of 3 days to pressure wash and paint, depending on the weather. P&R

Saturday, May 28, 2016

Porch Lights - Villas

If you purchased a porch light, at your expense, and would like it installed by the electrician, please go below to "Comments"  and leave your name, address, and phone number.

Contact Tim Kosloski Electric  727-455-4321, should you want him to install the light. Monies need to be paid directly to the electrician, Tim.
PAYMENT DOES NOT GO THROUGH AMERI-TECH

Here is a sample picture of a porch light being used by some owners. Purchased from Lowe's:


Sunday, May 22, 2016

How were the colors selected?

Most residents preferred Gettysburg Grey color when asked previously, so the Board hired Klar and Klar Architects to come up with 2 complimentary palettes and determine how they would best be applied to the community.  One of the proposals was selected, approved by the Board and is now being utilized.

Wednesday, May 18, 2016

Can the gates on LV be painted black?


Gates will not be painted black. They are going to be the same color as the garages. Architect felt it would stand out too much in black. 

Wednesday, May 11, 2016

Phone call generated via the blog: Weatherstripping stuck to the door, what needs to be done to fix it?

Response from Craig:
To fix this problem  I will have to remove  the weather  stripping and touch up the door then reinstall  the weather stripping  in a couple  of days  I will need access  to inside the home


P&R will no longer replace weatherstripping effective 8/24/16

Friday, May 6, 2016

Will P&R Replace the Weather Stripping in the Door?

Yes, P&R will replace the weather stripping in the front door at your request. The cost is $25.00. Please get with Craig, site manager, and inform him that you want it done.



What Buildings Have the Final Colors

The two villas closest to the tennis court are the final base colors for the community:


1761/1763 is Gettysburg Gray (Base #1)
1759/1757 is Serengeti Sand (Base #2)


When will Arabian Lane Townhouses get their proposals?


Proposals should have been delivered to those town homes on Arabian Lane that P&R deemed needed repairs.

You, as the owner, can either sign P&R proposal, pay them and have P&R perform the repairs or you can have repairs done by someone else,  BUT P&R must approve all repairs before they will approve the unit for painting.

After the units are pressure washed, P&R may ascertain repairs are needed before the unit is to be painted. P&R will submit a proposal to you for those repairs. Again, you may either have P&R repair the unit or have the repairs performed by someone else, BUT P&R must approve all repairs.

Wednesday, May 4, 2016

Can I refuse to have my front door painted?

No, the exterior of the buildings are maintained by the HOA and ALL units/buildings will be painted uniformly and according to the architect's specifications. NO wood door will be allowed to remain wood color but will be painted the color as approved.